MISO-J3021
235 MW generation in Lyon, MN · In queue since September 2022 · Proposed COD June 2027
235 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2027
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-01
MISO-J3021 is a proposed solar generation project with a total capacity of 235 MW, located in Lyon County, Minnesota. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of September 14, 2022. Northern States Power Company is the interconnecting utility. The proposed commercial operation date is June 1, 2027.
The project's interconnection status is currently in the Cluster Study phase. The point of interconnection (POI) is the Lake Yankton to Lyon County 115kV line. The project has appeared in recent news coverage regarding renewable energy development in the MISO region.
Generated from interconnection queue and public data sources
State
MN
County
Lyon
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
NORTHERN STATES POWER COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Lake Yankton to Lyon County 115kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.