100 MW hybrid in Perry, MS · In queue since September 2022 · Proposed COD June 2027
100 MW
Capacity
1
Components
Solar
3y 8m
In Queue
—
IA Status
COD target: 2027
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-01
MISO-J3028 is a proposed 100 MW hybrid solar and battery energy storage project located in Perry County, Mississippi. The project, which consists of 100 MW of solar generation, is being developed by Cooperative Energy.
The project is currently active in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of September 14, 2022. The proposed commercial operation date is June 1, 2027. The point of interconnection is the Hintonville to Waynesboro 161 kV line.
Generated from interconnection queue and public data sources
State
MS
County
Perry
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
COOPERATIVE ENERGY
Entity
MISO
Service Type
—
Point of Interconnection
Hintonville to Waynesboro 161 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3028