MISO-J3030
450 MW hybrid in Jefferson, AR · In queue since September 2022 · Proposed COD June 2027
450 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-01
MISO-J3030 is a proposed 450 MW hybrid solar and battery project located in Jefferson County, Arkansas. The project, which consists of 450 MW of solar power, is in the MISO interconnection queue, with an entry date of September 14, 2022. Entergy Arkansas is the utility associated with the project.
The proposed commercial operation date for MISO-J3030 is June 1, 2027. Its interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the White Bluff to Sheridan 500kV line. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
AR
County
Jefferson
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY ARKANSAS
Entity
MISO
Service Type
—
Point of Interconnection
White Bluff to Sheridan 500kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ARKANSAS.HUB
- Hub Confidence
- HIGH
- POI Substation
- Sheridan
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.