MISO-J3039
200 MW generation in Olmsted, MN · In queue since September 2022 · Proposed COD August 2027
200 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2027
Total Duration
4y 11m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-08-31
MISO-J3039 is a proposed 200 MW solar generation project located in Olmsted County, Minnesota. The project, under development by Southern Minnesota Municipal Power Agency, entered the Midcontinent Independent System Operator (MISO) interconnection queue on September 13, 2022. Its proposed commercial operation date is August 31, 2027. The project's interconnection status is currently in the Cluster Study phase, and its point of interconnection is the Byron 161kV substation.
The proposed project consists of 200 MW of solar photovoltaic generation. It is currently listed as an active project within the MISO interconnection queue.
Generated from interconnection queue and public data sources
State
MN
County
Olmsted
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
SOUTHERN MINNESOTA MUNICIPAL POWER AGENCY
Entity
MISO
Service Type
—
Point of Interconnection
Byron 161kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Byron Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3039