300 MW generation in Orange, TX · In queue since September 2022 · Proposed COD October 2026
300 MW
Capacity
1
Components
Solar
3y 8m
In Queue
—
IA Status
COD target: 2026
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-10-01
MISO-J3045 is a proposed 300 MW solar generation project located in Orange County, Texas. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of September 14, 2022. The proposed commercial operation date is October 1, 2026. The interconnecting utility is Entergy Texas, Inc.
The project consists of 300 MW of solar photovoltaic generation. It is currently listed as "active" in the MISO queue. The point of interconnection is the Chisholm RD- Hartburg 230kV substation.
Generated from interconnection queue and public data sources
State
TX
County
Orange
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY TEXAS, INC.
Entity
MISO
Service Type
—
Point of Interconnection
Chisholm RD- Hartburg 230kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- TEXAS.HUB
- Hub Confidence
- HIGH
- POI Substation
- Chisholm
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.