MISO-J3050
300 MW generation in Calhoun, MI · In queue since September 2022 · Proposed COD April 2027
300 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-04-01
MISO-J3050 is a proposed solar generation project with a total capacity of 300 MW, located in Calhoun County, Michigan. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on September 15, 2022. The proposed commercial operation date is April 1, 2027. The project's interconnection agreement status is listed as "In Progress (unknown study)".
The project, which is being developed within the Michigan Electric Transmission Company (METC) service area, consists of 300 MW of solar photovoltaic generation. The point of interconnection is the Oneida to Majestic 345 kV line.
Generated from interconnection queue and public data sources
State
MI
County
Calhoun
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
Oneida to Majestic 345 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3050