MISO-J3051
150 MW generation in Chisago, MN · In queue since January 2024 · Proposed COD June 2026
150 MW
Capacity
1
Components
Solar
2y 4m
In Queue
Cluster Study
IA Status
COD target: 2026
Total Duration
2y 5m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-06-30
MISO-J3051 is a proposed 150 MW solar generation project located in Chisago County, Minnesota. The project, under consideration by Great River Energy, entered the MISO interconnection queue on January 9, 2024, with a proposed commercial operation date of June 30, 2026. Its interconnection status is currently in the Cluster Study phase.
The development project consists of 150 MW of solar photovoltaic generation. The point of interconnection is the Rush City 230 kV substation. The project has appeared in recent news coverage regarding renewable energy development in the region.
Generated from interconnection queue and public data sources
State
MN
County
Chisago
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
GREAT RIVER ENERGY
Entity
MISO
Service Type
—
Point of Interconnection
Rush City 230 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3051