MISO-J3065
20 MW generation in Oceana, MI · In queue since September 2022 · Proposed COD March 2025
20 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
2y 6m
Schedule
13 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-03-30
MISO-J3065 is a proposed solar generation project located in Oceana County, Michigan, within the Midcontinent Independent System Operator (MISO) region. The project, with a total capacity of 20 MW, consists entirely of solar photovoltaic technology. Its interconnection request was filed on September 15, 2022, with a proposed commercial operation date of March 30, 2025. The project's interconnection agreement status is currently listed as "In Progress (unknown study)".
The designated point of interconnection (POI) for MISO-J3065 is the Donaldson 138 kV Bus. The project is within the service territory of utility METC.
Generated from interconnection queue and public data sources
State
MI
County
Oceana
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
Donaldson 138 kV Bus
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Donaldson Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3065