MISO-J3076
770 MW hybrid in Wabash, IL · In queue since September 2022 · Proposed COD November 2025
770 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2025
Total Duration
3y 2m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-11-30
MISO-J3076 is a proposed 770 MW hybrid solar and battery project located in Wabash County, Illinois. The project, which consists of 770 MW of solar capacity, is in the MISO interconnection queue, having entered on September 15, 2022. The proposed commercial operation date is November 30, 2025. The interconnecting utility is Ameren Illinois.
The project's interconnection status is currently in the Cluster Study phase. The point of interconnection is the 08GiBSON (PSI) to 7ALBION 345 kV line.
Generated from interconnection queue and public data sources
State
IL
County
Wabash
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
08GiBSON (PSI) to 7ALBION 345 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.