MISO-J3078
252 MW generation in Peoria, IL · In queue since September 2022 · Proposed COD October 2026
252 MW
Capacity
1
Components
Wind
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2026
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-10-31
The proposed MISO-J3078 project is a 252 MW wind generation facility located in Peoria County, Illinois. Interconnection to the Ameren Transmission Company of Illinois system is requested via the Fargo to Sandburg 345kV point of interconnection. The project entered the MISO interconnection queue on September 12, 2022, and has a proposed commercial operation date of October 31, 2026. Its interconnection status is currently in the Cluster Study phase.
The development project consists solely of 252 MW of wind generation capacity. It is currently listed as an active project within the MISO interconnection queue.
Generated from interconnection queue and public data sources
State
IL
County
Peoria
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN TRANSMISSION COMPANY OF ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
Fargo to Sandburg 345kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- AMIL.FARGO.MVP
- POI Substation
- Fargo
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.