MISO-J3082
135 MW hybrid in Franklin Parish, LA · In queue since September 2022 · Proposed COD June 2026
135 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-06-30
MISO-J3082 is a proposed 135 MW hybrid solar and battery project located in Franklin Parish, Louisiana. The project, which consists of 135 MW of solar generation, is in the Midcontinent Independent System Operator (MISO) interconnection queue. The queue entry date is September 15, 2022, with a proposed commercial operation date of June 30, 2026.
The interconnection agreement (IA) status is listed as "In Progress (unknown study)". The point of interconnection (POI) is on the 'Gilbert / 3GILBERT_LA (303322)' to 'Winnsboro / 3WINNSBORO! (337330)' 115kV line. The interconnecting utility is Entergy Louisiana.
Generated from interconnection queue and public data sources
State
LA
County
Franklin Parish
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY LOUISIANA
Entity
MISO
Service Type
—
Point of Interconnection
Taping the 'Gilbert / 3GILBERT_LA (303322)' to 'Winnsboro / 3WINNSBORO! (337330)' 115kV line.
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.