MISO-J3095
200 MW generation in Ford, IL · In queue since September 2022 · Proposed COD September 2025
200 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2025
Total Duration
3 years
Schedule
8 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-09-01
MISO-J3095 is a proposed 200 MW solar generation project located in Ford County, Illinois. The project, which interconnects with Ameren Illinois, entered the MISO interconnection queue on September 13, 2022, with a proposed commercial operation date of September 1, 2025.
The project's interconnection status is currently in the Cluster Study phase. The point of interconnection is at the 4PAXTON - 4J845POI 138.0kV location. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
IL
County
Ford
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
4PAXTON - 4J845POI 138.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3095