MISO-J3112
100 MW hybrid in Phillips, AR · In queue since September 2022 · Proposed COD June 2026
100 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-06-30
MISO-J3112 is a proposed 100 MW hybrid solar and battery project located in Phillips County, Arkansas. The project, which consists of 100 MW of solar capacity, is in the Midcontinent Independent System Operator (MISO) interconnection queue. Its queue entry date is September 15, 2022, with a proposed commercial operation date of June 30, 2026. The interconnection agreement (IA) status is currently listed as "In Progress (unknown study)". The point of interconnection is the Barton - West Helena 115kV line, and the interconnecting utility is Entergy Arkansas.
The development project is located within the MISO region. It is listed as an active project in the interconnection queue. Recent news coverage of the project is available.
Generated from interconnection queue and public data sources
State
AR
County
Phillips
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY ARKANSAS
Entity
MISO
Service Type
—
Point of Interconnection
Barton - West Helena 115kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ARKANSAS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3112