Queue ID
MISO-J3120
Capacity
200 MW
Technology
Solar+Battery
Status
active
Location
Jackson, AR
Region
MISO
Developer
IA Status
In Progress (unknown study)

MISO-J3120

MISO-J3120BetaActiveSolarBatteryMISOLBNL + Live

200 MW hybrid in Jackson, AR · In queue since September 2022 · Proposed COD June 2026

200 MW

Capacity

1

Components

Solar

3y 8m

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection

Total Duration

3y 9m

In Study38%
Queue EntrySep 15, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-06-30

About

MISO-J3120 is a proposed 200 MW hybrid solar and battery project located in Jackson County, Arkansas. The development project, with Entergy Arkansas as the utility, consists of 200 MW of solar capacity. It is listed as active in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of September 15, 2022, and a proposed commercial operation date of June 30, 2026.

The interconnection agreement (IA) status for MISO-J3120 is currently "In Progress (unknown study)". The point of interconnection (POI) is the Taping 'Newport AB / NEWPORTSOLAR (338177)' to 'Cash / 5CASH (338171)' 161kV Line.

Generated from interconnection queue and public data sources

Project Details

State

AR

County

Jackson

Grid Region

MISO (Midcontinent)

Market

ISO/RTO Member

Developer

Utility

ENTERGY ARKANSAS

Entity

MISO

Service Type

Point of Interconnection

Taping 'Newport AB / NEWPORTSOLAR (338177)' to 'Cash / 5CASH (338171)' 161kV Line.

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
MISO
Trading Hub
ARKANSAS.HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project MISO-J3120