MISO-J3122
200 MW hybrid in Crittenden, AR · In queue since September 2022 · Proposed COD April 2025
200 MW
Capacity
1
Components
Wind
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
2y 7m
Schedule
13 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-04-15
MISO-J3122 is a proposed 200 MW hybrid wind and battery project located in Crittenden County, Arkansas. The development project, consisting of 200 MW of wind generation, is in the Midcontinent Independent System Operator (MISO) interconnection queue. The queue entry date is September 14, 2022, with a proposed commercial operation date of April 15, 2025.
The interconnection agreement (IA) status for MISO-J3122 is listed as "In Progress (unknown study)". The interconnecting utility is Entergy Arkansas. The point of interconnection (POI) is BOB WHITE.
Generated from interconnection queue and public data sources
State
AR
County
Crittenden
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY ARKANSAS
Entity
MISO
Service Type
—
Point of Interconnection
BOB WHITE
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ARKANSAS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3122