MISO-J3124
120 MW generation in Saginaw, MI · In queue since September 2022 · Proposed COD August 2026
120 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3y 11m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-08-31
The proposed MISO-J3124 project is a 120 MW solar generation facility located in Saginaw County, Michigan. The project was entered into the Midcontinent Independent System Operator (MISO) interconnection queue on September 14, 2022, with a proposed commercial operation date of August 31, 2026. The interconnecting utility is METC.
The interconnection agreement (IA) for the project is currently listed as "In Progress (unknown study)". The point of interconnection (POI) is the Murphy 345 kV Substation.
Generated from interconnection queue and public data sources
State
MI
County
Saginaw
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
Murphy 345 kV Substation
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Murphy Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.