Project MISO-J3128 — Project Summary

Queue ID
MISO-J3128
Capacity
100 MW
Technology
Solar
Status
active
Location
East Feliciana Parish, LA
Region
MISO
Developer
IA Status
In Progress (unknown study)

MISO-J3128

MISO-J3128BetaActiveSolarMISOLBNL + Live

100 MW generation in East Feliciana Parish, LA · In queue since September 2022 · Proposed COD October 2026

100 MW

Capacity

1

Components

Solar

3y 8m

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection

Total Duration

4y 1m

In Study38%
Queue EntrySep 15, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-10-01

About

MISO-J3128 is a proposed 100 MW solar generation project located in East Feliciana Parish, Louisiana. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an initial queue entry date of September 15, 2022. The proposed commercial operation date is October 1, 2026. Entergy Louisiana is the utility associated with the project.

The interconnection agreement (IA) status for MISO-J3128 is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Starhill Substation 138 kV. The project has appeared in recent news coverage regarding renewable energy developments in the MISO region.

Generated from interconnection queue and public data sources

Project Details

State

LA

County

East Feliciana Parish

Grid Region

MISO (Midcontinent)

Market

ISO/RTO Member

Developer

Utility

ENTERGY LOUISIANA

Entity

MISO

Service Type

Point of Interconnection

Starhill Substation 138 kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
MISO
Trading Hub
LOUISIANA.HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project MISO-J3128