MISO-J3134
150 MW generation in Otsego, MI · In queue since September 2022 · Proposed COD June 2025
150 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
2y 9m
Schedule
10 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-06-30
MISO-J3134 is a proposed solar generation project located in Otsego County, Michigan, with a total capacity of 150 MW. The project, developed by Wolverine Power Supply Cooperative, entered the Midcontinent Independent System Operator (MISO) interconnection queue on September 15, 2022. Its proposed commercial operation date is June 30, 2025.
The interconnection agreement for MISO-J3134 is currently in progress, with the specific study phase unknown. The point of interconnection is the Gaylord Transmission Station at 138 kV, Bus #263662. The project consists of 150 MW of solar photovoltaic generation.
Generated from interconnection queue and public data sources
State
MI
County
Otsego
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
WOLVERINE POWER SUPPLY COOPERATIVE
Entity
MISO
Service Type
—
Point of Interconnection
Gaylord Transmission Station, 138 kV, Bus #263662
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3134