MISO-J3145
150 MW generation in Putnam, IN · In queue since September 2022 · Proposed COD July 2027
150 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2027
Total Duration
4y 10m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-07-01
MISO-J3145 is a proposed 150 MW solar generation project located in Putnam County, Indiana. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of September 14, 2022. The proposed commercial operation date is July 1, 2027. Duke Energy Indiana is the utility associated with the project. Its interconnection status is currently in the Cluster Study phase.
The proposed project consists of 150 MW of solar photovoltaic generation. The point of interconnection is the Amo - Wheatland Line.
Generated from interconnection queue and public data sources
State
IN
County
Putnam
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
DUKE ENERGY INDIANA
Entity
MISO
Service Type
—
Point of Interconnection
Amo - Wheatland Line
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.