MISO-J3151
150 MW generation in Sheboygan, WI · In queue since September 2022 · Proposed COD September 2025
150 MW
Capacity
1
Components
Gas
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3 years
Schedule
8 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-09-01
MISO-J3151 is a proposed 150 MW gas-fired generation project located in Sheboygan County, Wisconsin. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on September 15, 2022. The proposed commercial operation date is September 1, 2025.
The interconnection agreement for MISO-J3151 with American Transmission Company is currently in progress, with the specific study phase unknown. The point of interconnection is Sheboygan Falls.
Generated from interconnection queue and public data sources
State
WI
County
Sheboygan
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMERICAN TRANSMISSION COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Sheboygan Falls
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- South Sheboygan Falls
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3151