MISO-J3154
160 MW generation in Franklin, IA · In queue since September 2022 · Proposed COD April 2027
160 MW
Capacity
1
Components
Gas
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2027
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-04-01
MISO-J3154 is a proposed 160 MW gas-fired generation project located in Franklin County, Iowa. The project, which is being developed by MidAmerican Energy Co., entered the MISO interconnection queue on September 15, 2022, with a proposed commercial operation date of April 1, 2027. Its point of interconnection is the Blackhawk (MEC) - Quinn 345 substation, shared with project J2892. The project's interconnection status is currently in the Cluster Study phase.
Generated from interconnection queue and public data sources
State
IA
County
Franklin
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
MIDAMERICAN ENERGY CO.
Entity
MISO
Service Type
—
Point of Interconnection
Blackhawk (MEC) - Quinn 345 (shared POI with J2892)
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3154