Project MISO-J3154 — Project Summary

Queue ID
MISO-J3154
Capacity
160 MW
Technology
Gas
Status
active
Location
Franklin, IA
Region
MISO
Developer
IA Status
Cluster Study

MISO-J3154

MISO-J3154BetaActiveGasMISOLBNL + Live

160 MW generation in Franklin, IA · In queue since September 2022 · Proposed COD April 2027

160 MW

Capacity

1

Components

Gas

3y 8m

In Queue

Cluster Study

IA Status

COD target: 2027

Interconnection

Total Duration

4y 7m

Impact Study25%
Queue EntrySep 15, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-04-01

About

MISO-J3154 is a proposed 160 MW gas-fired generation project located in Franklin County, Iowa. The project, which is being developed by MidAmerican Energy Co., entered the MISO interconnection queue on September 15, 2022, with a proposed commercial operation date of April 1, 2027. Its point of interconnection is the Blackhawk (MEC) - Quinn 345 substation, shared with project J2892. The project's interconnection status is currently in the Cluster Study phase.

Generated from interconnection queue and public data sources

Project Details

State

IA

County

Franklin

Grid Region

MISO (Midcontinent)

Market

ISO/RTO Member

Developer

Utility

MIDAMERICAN ENERGY CO.

Entity

MISO

Service Type

Point of Interconnection

Blackhawk (MEC) - Quinn 345 (shared POI with J2892)

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
MISO
Trading Hub
MINN.HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project MISO-J3154