MISO-J3162
100 MW storage in Rock, WI · In queue since September 2022 · Proposed COD June 2027
100 MW
Capacity
1
Components
Battery
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-30
MISO-J3162 is a proposed 100 MW battery storage project located in Rock County, Wisconsin. The project is interconnected within the Midcontinent Independent System Operator (MISO) region. The queue entry date is September 14, 2022, with a proposed commercial operation date of June 30, 2027. The point of interconnection is the Beloit Gateway 138 kV substation.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The transmission utility is American Transmission Company.
Generated from interconnection queue and public data sources
State
WI
County
Rock
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMERICAN TRANSMISSION COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Beloit Gateway 138 kV substation
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Beloit Gateway
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3162