MISO-J3170
200 MW generation in Avoyelles Parish, LA · In queue since September 2022 · Proposed COD June 2026
200 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-06-30
MISO-J3170 is a proposed 200 MW solar generation project located in Avoyelles Parish, Louisiana. The project, which entered the Midcontinent Independent System Operator (MISO) interconnection queue on September 13, 2022, is being developed by CLECO POWER. Its proposed commercial operation date is June 30, 2026.
The interconnection agreement for MISO-J3170 is currently listed as "In Progress (unknown study)". The point of interconnection is the Eola-Marksville 138 kV line. The project is listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
LA
County
Avoyelles Parish
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
CLECO POWER
Entity
MISO
Service Type
—
Point of Interconnection
Eola-Marksville 138 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3170