160 MW generation in Tunica, MS · In queue since September 2022 · Proposed COD October 2026
160 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-10-01
MISO-J3175 is a proposed solar generation project with a total capacity of 160 MW, located in Tunica County, Mississippi. The project is interconnected within the Midcontinent Independent System Operator (MISO) region and is being developed for Entergy Mississippi, LLC. The project consists of 160 MW of solar photovoltaic generation.
The project entered the MISO interconnection queue on September 14, 2022, with a proposed commercial operation date of October 1, 2026. Its interconnection agreement status is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
MS
County
Tunica
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY MISSISSIPPI, LLC.
Entity
MISO
Service Type
—
Point of Interconnection
Robinsonville 230kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3175