MISO-J3186
100 MW hybrid in Bolivar, MS · In queue since September 2022 · Proposed COD January 2027
100 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 4m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-01-01
MISO-J3186 is a proposed 100 MW hybrid solar and battery energy storage project located in Bolivar County, Mississippi. The project, which consists of 100 MW of solar generation, is in the Midcontinent Independent System Operator (MISO) interconnection queue. The queue entry date is September 15, 2022, with a proposed commercial operation date of January 1, 2027. The interconnecting utility is Entergy Mississippi, LLC.
The interconnection agreement (IA) status for MISO-J3186 is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Rosedale - Delta 115 kV substation. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
MS
County
Bolivar
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY MISSISSIPPI, LLC.
Entity
MISO
Service Type
—
Point of Interconnection
Rosedale - Delta 115 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.