Project MISO-J3198 — Project Summary

Queue ID
MISO-J3198
Capacity
80 MW
Technology
Solar+Battery
Status
active
Location
Barron, WI
Region
MISO
Developer
IA Status
Cluster Study

MISO-J3198

MISO-J3198BetaActiveSolarBatteryMISOLBNL + Live

80 MW hybrid in Barron, WI · In queue since September 2022 · Proposed COD December 2026

80 MW

Capacity

1

Components

Solar

3y 8m

In Queue

Cluster Study

IA Status

COD target: 2026

Interconnection

Total Duration

4y 3m

Impact Study25%
Queue EntrySep 15, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-22

About

MISO-J3198 is a proposed 80 MW hybrid solar and battery project located in Barron County, Wisconsin. The project, which consists of 80 MW of solar generation, is in the MISO interconnection queue as of September 15, 2022, with a proposed commercial operation date of December 22, 2026. The interconnecting utility is Dairyland Power Cooperative.

The project's interconnection status is currently in the Cluster Study phase.

Generated from interconnection queue and public data sources

Project Details

State

WI

County

Barron

Grid Region

MISO (Midcontinent)

Market

ISO/RTO Member

Developer

Utility

DAIRYLAND POWER COOPERATIVE

Entity

MISO

Service Type

Point of Interconnection

Barron 161KV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
MISO
Trading Hub
MINN.HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project MISO-J3198