MISO-J3204
208 MW generation in Clark, WI · In queue since September 2022 · Proposed COD September 2025
208 MW
Capacity
1
Components
Wind
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2025
Total Duration
3 years
Schedule
8 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-09-15
The proposed MISO-J3204 project is a 208 MW wind generation project located in Clark County, Wisconsin. The project is interconnected to the American Transmission Company via the Gardner Park - Stone Lake 345kV Line. It entered the MISO interconnection queue on September 14, 2022, with a proposed commercial operation date of September 15, 2025. Its interconnection status is currently in the Cluster Study phase.
The development project consists of 208 MW of wind capacity. The project is listed in the MISO interconnection queue.
Generated from interconnection queue and public data sources
State
WI
County
Clark
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMERICAN TRANSMISSION COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Gardner Park - Stone Lake 345kV Line
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3204