MISO-J3209
467 MW generation in Rapides Parish, LA · In queue since September 2022 · Proposed COD March 2026
467 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3y 6m
Schedule
2 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-03-01
MISO-J3209 is a proposed solar generation project with a total capacity of 467 MW. The project is located in Rapides Parish, Louisiana, and is being developed within the Midcontinent Independent System Operator (MISO) region. The queue entry date for MISO-J3209 is September 15, 2022, with a proposed commercial operation date of March 1, 2026. The interconnecting utility is CLECO POWER.
The interconnection agreement for MISO-J3209 is currently listed as "In Progress (unknown study)". The point of interconnection (POI) is the Hineston 230kV Substation. The project has appeared in the MISO interconnection queue but has not been linked to any existing operating plants or recent news coverage in the energy data platform.
Generated from interconnection queue and public data sources
State
LA
County
Rapides Parish
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
CLECO POWER
Entity
MISO
Service Type
—
Point of Interconnection
Hineston 230kV Substation
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- HIGH
- POI Substation
- Hineston Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.