MISO-J3213
51 MW generation in Hennepin, MN · In queue since September 2022 · Proposed COD December 2026
51 MW
Capacity
1
Components
Gas
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2026
Total Duration
4y 3m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
The proposed MISO-J3213 project is a 51 MW natural gas generation facility located in Hennepin County, Minnesota. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of September 1, 2022, and a proposed commercial operation date of December 31, 2026. The interconnecting utility is Northern States Power Company.
The project's interconnection status is currently in the Cluster Study phase. The point of interconnection (POI) is the Riverside 115kV Substation.
Generated from interconnection queue and public data sources
State
MN
County
Hennepin
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
NORTHERN STATES POWER COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Riverside 115kV Substation
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Riverside Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.