MISO-J3236
200 MW storage in Chisago, MN · In queue since March 2024 · Proposed COD January 2028
200 MW
Capacity
1
Components
Battery
2y 2m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 10m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-01-15
MISO-J3236 is a proposed 200 MW battery storage project located in Chisago County, Minnesota. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue as of March 28, 2024, with a proposed commercial operation date of January 15, 2028. The interconnecting utility is Northern States Power Company.
The development project consists solely of battery storage, with a total capacity of 200 MW. It is currently listed as active in the MISO queue and intends to interconnect at the Chisago County 115kV Substation.
Generated from interconnection queue and public data sources
State
MN
County
Chisago
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
NORTHERN STATES POWER COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Chisago County 115kV Substation
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3236