MISO-J3251
200 MW storage in Genesee, MI · In queue since April 2024 · Proposed COD June 2028
200 MW
Capacity
1
Components
Battery
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-01
MISO-J3251 is a proposed 200 MW battery storage project located in Genesee County, Michigan. The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of April 15, 2024. The proposed commercial operation date is June 1, 2028. The interconnecting utility is METC.
The development project consists solely of battery storage, with a total capacity of 200 MW. As of the latest data, the project's interconnection status is listed as active. There is no information available regarding an interconnection agreement (IA) or news coverage.
Generated from interconnection queue and public data sources
State
MI
County
Genesee
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
THETFORD
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- CONS.GENESEESO
- POI Substation
- Thetford Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.