MISO-J3254
175 MW hybrid in Pulaski, IL · In queue since April 2024 · Proposed COD December 2026
175 MW
Capacity
1
Components
Solar
2y 1m
In Queue
—
IA Status
COD target: 2026
Total Duration
2y 8m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-30
MISO-J3254 is a proposed 175 MW hybrid solar and battery energy storage project located in Pulaski County, Illinois. The project, which consists of 175 MW of solar generation, is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of April 15, 2024. The proposed commercial operation date is December 30, 2026.
The project is interconnected with Ameren Missouri at the 5CAPE GIR3 - 5JOPPA SR 161.0kV point of interconnection. As of the current data, the project's interconnection agreement (IA) status is not specified. The project is currently listed as active in the MISO queue.
Generated from interconnection queue and public data sources
State
IL
County
Pulaski
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN MISSOURI
Entity
MISO
Service Type
—
Point of Interconnection
5CAPE GIR3 - 5JOPPA SR 161.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3254