MISO-J3268
100 MW storage in Gratiot, MI · In queue since April 2024 · Proposed COD September 2027
100 MW
Capacity
1
Components
Battery
2y 1m
In Queue
—
IA Status
COD target: 2027
Total Duration
3y 5m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-09-10
MISO-J3268 is a proposed 100 MW battery storage project located in Gratiot County, Michigan. The project, under consideration in the Midcontinent Independent System Operator (MISO) interconnection queue, was entered on April 18, 2024. The proposed commercial operation date is September 10, 2027. The interconnecting utility is Michigan Electric Transmission Company (METC).
The project is currently listed as active in the MISO queue. No Interconnection Agreement (IA) status is available. There is no identified developer or news coverage associated with this project at this time.
Generated from interconnection queue and public data sources
State
MI
County
Gratiot
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
REGAL
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- CONS.PNRVR.SOL
- POI Substation
- Regal Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3268