Project MISO-J3275 — Project Summary

Queue ID
MISO-J3275
Capacity
249 MW
Technology
Wind
Status
active
Location
Benton, MN
Region
MISO
Developer
IA Status

MISO-J3275

MISO-J3275BetaActiveWindMISOLBNL + Live

249 MW generation in Benton, MN · In queue since April 2024 · Proposed COD September 2028

249 MW

Capacity

1

Components

Wind

2y 1m

In Queue

IA Status

COD target: 2028

Interconnection

Total Duration

4y 5m

Pre-Study0%
Queue EntryApr 17, 2024

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-09-04

About

MISO-J3275 is a proposed wind generation project with a total capacity of 249 MW, located in Benton County, Minnesota. The project is being developed by Great River Energy and interconnected within the Midcontinent Independent System Operator (MISO) region.

The project entered the MISO interconnection queue on April 17, 2024, with a proposed commercial operation date of September 4, 2028. The point of interconnection is the Mud Lake - Benton County (GRE) 230kV substation. The project's interconnection status is currently active.

Generated from interconnection queue and public data sources

Project Details

State

MN

County

Benton

Grid Region

MISO (Midcontinent)

Market

ISO/RTO Member

Developer

Utility

GREAT RIVER ENERGY

Entity

MISO

Service Type

Point of Interconnection

Mud Lake - Benton County (GRE) 230kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
MISO
Trading Hub
MINN.HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.