MISO-J3280
300 MW generation in Dickey, ND · In queue since April 2024 · Proposed COD September 2028
300 MW
Capacity
1
Components
Wind
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-01
MISO-J3280 is a proposed 300 MW wind generation project located in Dickey County, North Dakota. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue as of April 17, 2024, with a proposed commercial operation date of September 1, 2028. Montana-Dakota Utilities Co. is the interconnecting utility.
The project, consisting of 300 MW of wind capacity, is currently listed as active in the MISO queue. The point of interconnection (POI) is the Ellendale 345 kV substation.
Generated from interconnection queue and public data sources
State
ND
County
Dickey
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
MONTANA-DAKOTA UTILITIES CO.
Entity
MISO
Service Type
—
Point of Interconnection
Ellendale 345
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Ellendale Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.