Project MISO-J3280 — Project Summary

Queue ID
MISO-J3280
Capacity
300 MW
Technology
Wind
Status
active
Location
Dickey, ND
Region
MISO
Developer
IA Status

MISO-J3280

MISO-J3280BetaActiveWindMISOLBNL + Live

300 MW generation in Dickey, ND · In queue since April 2024 · Proposed COD September 2028

300 MW

Capacity

1

Components

Wind

2y 1m

In Queue

IA Status

COD target: 2028

Interconnection

Total Duration

4y 5m

Pre-Study0%
Queue EntryApr 17, 2024

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-09-01

About

MISO-J3280 is a proposed 300 MW wind generation project located in Dickey County, North Dakota. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue as of April 17, 2024, with a proposed commercial operation date of September 1, 2028. Montana-Dakota Utilities Co. is the interconnecting utility.

The project, consisting of 300 MW of wind capacity, is currently listed as active in the MISO queue. The point of interconnection (POI) is the Ellendale 345 kV substation.

Generated from interconnection queue and public data sources

Project Details

State

ND

County

Dickey

Grid Region

MISO (Midcontinent)

Market

ISO/RTO Member

Developer

Utility

MONTANA-DAKOTA UTILITIES CO.

Entity

MISO

Service Type

Point of Interconnection

Ellendale 345

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
MISO
Trading Hub
MINN.HUB
Hub Confidence
HIGH
POI Substation
Ellendale Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project MISO-J3280