MISO-J3282
297 MW generation in Mason, MI · In queue since April 2024 · Proposed COD November 2028
297 MW
Capacity
1
Components
Solar
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-11-01
MISO-J3282 is a proposed solar generation project located in Mason County, Michigan, with a total capacity of 297 MW. The project, which consists entirely of solar photovoltaic generation, is in the Midcontinent Independent System Operator (MISO) interconnection queue, under queue ID MISO-J3282. The queue entry date is April 15, 2024, and the proposed commercial operation date is November 1, 2028. The interconnecting utility is METC.
The point of interconnection (POI) for the project is the KEYSTONE - LUDINGTON 345.0kV line. As of the latest data, the project is listed as active in the MISO queue. There is no information available regarding an interconnection agreement (IA) status, developer, or news coverage.
Generated from interconnection queue and public data sources
State
MI
County
Mason
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
KEYSTONE - LUDINGTON 345.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3282