MISO-J3287
200 MW generation in Osceola, MI · In queue since April 2024 · Proposed COD November 2028
200 MW
Capacity
1
Components
Solar
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-11-01
MISO-J3287 is a proposed solar generation project located in Osceola County, Michigan, with a total capacity of 200 MW. The project, developed by Wolverine Power Supply Cooperative, consists of 200 MW of solar photovoltaic generation. It is currently active in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of April 15, 2024, and a proposed commercial operation date of November 1, 2028.
The point of interconnection for MISO-J3287 is the Hersey - Baldwin 138.0kV line.
Generated from interconnection queue and public data sources
State
MI
County
Osceola
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
WOLVERINE POWER SUPPLY COOPERATIVE
Entity
MISO
Service Type
—
Point of Interconnection
Hersey - Baldwin 138.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3287