MISO-J3289
35 MW generation in Sherburne, MN · In queue since April 2024 · Proposed COD June 2025
35 MW
Capacity
1
Components
Gas
2y 1m
In Queue
—
IA Status
COD target: 2025
Total Duration
1y 2m
Schedule
11 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-06-01
MISO-J3289 is a proposed 35 MW gas-fired generation project located in Sherburne County, Minnesota. The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of April 17, 2024. Great River Energy is the utility associated with the project. The proposed commercial operation date is June 1, 2025.
The project is currently listed as active in the MISO queue. The point of interconnection (POI) is at Elk River 14. There is no interconnection agreement (IA) status available in the provided data, nor is there any indication of a link to an existing operating plant or recent news coverage.
Generated from interconnection queue and public data sources
State
MN
County
Sherburne
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
GREAT RIVER ENERGY
Entity
MISO
Service Type
—
Point of Interconnection
ELK RIVER 14
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- GRE.ELKRI4
- POI Substation
- Elk River Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3289