MISO-J3291
200 MW storage in Lagrange, IN · In queue since April 2024 · Proposed COD September 2028
200 MW
Capacity
1
Components
Battery
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-15
MISO-J3291 is a proposed 200 MW battery storage project located in Lagrange County, Indiana. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of April 17, 2024. The proposed commercial operation date is September 15, 2028. The designated utility is Northern Indiana Public Service Company.
The project consists of a 200 MW battery energy storage system. As of the current data, the project is listed as active in the interconnection queue. There is no information available regarding an executed interconnection agreement or news coverage.
Generated from interconnection queue and public data sources
State
IN
County
Lagrange
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
NORTHERN INDIANA PUBLIC SERVICE COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
HIPLE
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- HIGH
- POI Substation
- Hiple Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3291