MISO-J3313
263 MW generation in Lenawee, MI · In queue since April 2024 · Proposed COD September 2028
263 MW
Capacity
1
Components
Wind
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-01
MISO-J3313 is a proposed wind generation project located in Lenawee County, Michigan, with a total capacity of 263 MW. The project, which consists entirely of wind turbines, is listed in the Midcontinent Independent System Operator (MISO) interconnection queue under queue ID MISO-J3313. The queue entry date is April 16, 2024, and the proposed commercial operation date is September 1, 2028. The interconnecting utility is METC.
The point of interconnection (POI) for the project is the MOROCCO - ALLEN JUNCTION 345.0kV. The project is currently listed as active in the interconnection queue. Recent news coverage has discussed the project.
Generated from interconnection queue and public data sources
State
MI
County
Lenawee
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
MOROCCO - ALLEN JUNCTION 345.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Junction