MISO-J3326
250 MW generation in Lyon, MN · In queue since April 2024 · Proposed COD May 2028
250 MW
Capacity
1
Components
Wind
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-05-01
MISO-J3326 is a proposed 250 MW wind generation project located in Lyon County, Minnesota. The project, which entered the Midcontinent Independent System Operator (MISO) interconnection queue on April 18, 2024, is targeting a commercial operation date of May 1, 2028. The interconnecting utility is Missouri River Energy Services - Transmission.
The point of interconnection (POI) is the Lyon County - Brookings County 345.0kV line. As of the current data, the project's interconnection agreement (IA) status is not specified. The project is currently listed as active in the MISO queue.
Generated from interconnection queue and public data sources
State
MN
County
Lyon
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
MISSOURI RIVER ENERGY SERVICES - TRANSMISSION
Entity
MISO
Service Type
—
Point of Interconnection
Lyon County - Brookings County 345.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.