MISO-J333
170 MW generation in IN · In queue since May 2014 · Proposed COD December 2010
170 MW
Capacity
1
Components
Coal
12 years
In Queue
IA Executed
IA Status
COD target: 2010
Total Duration
12 years
Schedule
187 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–36 months
Proposed COD: 2010-12-31
MISO-J333 is a proposed 170 MW coal generation project located in Indiana. The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue with a queue entry date of May 16, 2014. Its proposed commercial operation date (COD) is December 31, 2010, which is in the past.
The project's interconnection agreement (IA) status is listed as "IA Executed," indicating that an agreement has been reached with MISO. The point of interconnection (POI) is the Wabash River 230 kV Bus.
Generated from interconnection queue and public data sources
State
IN
County
—
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
MISO
Service Type
—
Point of Interconnection
Wabash River 230 kV Bus
Data Source
LBNL
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- HIGH
- POI Substation
- Wabash
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J333