MISO-J3331
470 MW generation in Sullivan, IN · In queue since April 2024 · Proposed COD May 2028
470 MW
Capacity
1
Components
Gas
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-05-01
MISO-J3331 is a proposed 470 MW natural gas generation project located in Sullivan County, Indiana. The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of April 17, 2024. Indianapolis Power & Light Company is the utility associated with the project. The proposed commercial operation date is May 1, 2028.
The point of interconnection (POI) for the project is the Petersburg - Sullivan (AEP/PJM) 345.0kV line. As of the latest data, the project's interconnection status is listed as active.
Generated from interconnection queue and public data sources
State
IN
County
Sullivan
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
INDIANAPOLIS POWER & LIGHT COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Petersburg - Sullivan (AEP/PJM) 345.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3331