MISO-J3340
175 MW generation in Vermilion, IL · In queue since March 2024 · Proposed COD September 2028
175 MW
Capacity
1
Components
Solar
2y 2m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 6m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-01
MISO-J3340 is a proposed solar generation project with a total capacity of 175 MW, located in Vermilion County, Illinois. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on March 18, 2024. The proposed commercial operation date is September 1, 2028. The point of interconnection is at the Rossville 138kV on the Hoopeston to Vermilion 138kV Line.
The project is being developed within the Ameren Illinois utility service area. As of the current data, the project has an active status in the MISO queue, and no interconnection agreement (IA) status is specified. Recent news coverage of the project is not indicated in the available data.
Generated from interconnection queue and public data sources
State
IL
County
Vermilion
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
Rossville 138kV on the Hoopeston to Vermilion 138kV Line
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3340