MISO-J3341
100 MW generation in Vermilion, IL · In queue since April 2024 · Proposed COD August 2028
100 MW
Capacity
1
Components
Wind
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 4m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-08-31
The proposed MISO-J3341 project is a 100 MW wind generation facility located in Vermilion County, Illinois. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of April 18, 2024. The proposed commercial operation date is August 31, 2028.
The project, which will interconnect with Ameren Illinois, is currently listed as active in the MISO queue. The point of interconnection is the 7BUNSONVILLE - 7SIDNEY 345.0kV line.
Generated from interconnection queue and public data sources
State
IL
County
Vermilion
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
7BUNSONVILLE - 7SIDNEY 345.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.