MISO-J3361
254 MW generation in Bay, MI · In queue since April 2024 · Proposed COD December 2027
254 MW
Capacity
1
Components
Wind
2y 1m
In Queue
—
IA Status
COD target: 2027
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-03
MISO-J3361 is a proposed wind generation project with a total capacity of 254 MW. The project is located in Bay County, Michigan, and is being developed within the Midcontinent Independent System Operator (MISO) region. The project entered the MISO interconnection queue on April 12, 2024, with a proposed commercial operation date of December 3, 2027.
The project is listed in the MISO queue under the utility METC. As of the latest data, the project's interconnection status is active, and it does not yet have an executed interconnection agreement. The point of interconnection is listed as "Other_".
Generated from interconnection queue and public data sources
State
MI
County
Bay
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
Other_
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3361