MISO-J3379
100 MW generation in Johnson, IL · In queue since April 2024 · Proposed COD February 2028
100 MW
Capacity
1
Components
Solar
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 10m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-02-18
MISO-J3379 is a proposed 100 MW solar generation project located in Johnson County, Illinois. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on April 18, 2024. The proposed commercial operation date is February 18, 2028. The interconnecting utility is Ameren Illinois.
The project consists of 100 MW of solar photovoltaic generation. As of the current data, an interconnection agreement (IA) has not been finalized. The point of interconnection (POI) is the 7JORD - 7MASS 345.0kV line.
Generated from interconnection queue and public data sources
State
IL
County
Johnson
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
7JORD - 7MASS 345.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3379