MISO-J3382
171 MW generation in Piatt, IL · In queue since April 2024 · Proposed COD September 2028
171 MW
Capacity
1
Components
Solar
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-30
MISO-J3382 is a proposed solar generation project with a total capacity of 171 MW, located in Piatt County, Illinois. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of April 18, 2024. The proposed commercial operation date is September 30, 2028. The interconnecting utility is Ameren Illinois.
The development project, sponsored within the MISO queue by the listed entity MISO, consists solely of solar photovoltaic generation. As of the latest data, the project's interconnection agreement (IA) status is not specified. The point of interconnection (POI) is at the 4WEEDMAN - 4MAHOMET 1 138.0kV location.
Generated from interconnection queue and public data sources
State
IL
County
Piatt
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
4WEEDMAN - 4MAHOMET 1 138.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3382