MISO-J3384
300 MW generation in Stevens, MN · In queue since April 2024 · Proposed COD October 2028
300 MW
Capacity
1
Components
Wind
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 6m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-10-31
MISO-J3384 is a proposed 300 MW wind generation project located in Stevens County, Minnesota. The project, under consideration by Great River Energy, entered the Midcontinent Independent System Operator (MISO) interconnection queue on April 17, 2024. Its proposed commercial operation date is October 31, 2028.
The project's point of interconnection is at the Ownership Change (OTP MORRIS) - JOHNSON JUNCTION 115.0kV. As of the latest data, the project remains in active status within the MISO queue.
Generated from interconnection queue and public data sources
State
MN
County
Stevens
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
GREAT RIVER ENERGY
Entity
MISO
Service Type
—
Point of Interconnection
Ownership Change (OTP MORRIS) - JOHNSON JUNCTION 115.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Junction
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3384