MISO-J3387
150 MW storage in Henry, IN · In queue since April 2024 · Proposed COD October 2026
150 MW
Capacity
1
Components
Battery
2y 1m
In Queue
—
IA Status
COD target: 2026
Total Duration
2y 6m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-10-01
MISO-J3387 is a proposed 150 MW battery storage project located in Henry County, Indiana. The project, which consists entirely of battery storage, is being developed within the Duke Energy Indiana service area. It is currently active in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of April 18, 2024. The proposed commercial operation date is October 1, 2026.
The project is interconnected at the Greensboro - New Castle 138 kV line. As of the latest data, the project does not have an executed interconnection agreement.
Generated from interconnection queue and public data sources
State
IN
County
Henry
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
DUKE ENERGY INDIANA
Entity
MISO
Service Type
—
Point of Interconnection
Greensboro - New Castle 138 138.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3387